10x10m Magnet Digital Dance Floor Order Case
November 26, 2019 — Placed the order (Paid 50% deposit by cash during LDI SHOW)
December 20, 2019— Began the Production( The factory produces the good according to the queue of payment)
January 15, 2020— Testing for 48 hours:
Because of Chinese Spring Festival and Covid-19. The Factory backed to work on March 1st, 2020.
March 30, 2020— Testing for 24 hours again:
Customer paid balance, then waiting for customer’ other products to ship together in one container.
April 9, 2020—Last testing and picked up the 400pcs by carton:

April 10, 2020—Container Shipping:
June 4, 2020—-Received the dance Floor